What is one benefit of having an IP iteration every PI?

  • A. It creates an estimating buffer for meeting PI objectives
  • B. It creates a chance for teams to manage quality
  • C. It creates a timeboxed opportunity for team growth
  • D. It creates a guardrail for teams working too hard


Answer : B

What is one element of the CALMR approach to DevOps?

  • A. Maximize work in process
  • B. Lean flow accelerates delivery
  • C. Relentlessly reduce risk
  • D. Activate the knowledge worker


Answer : B

What is the first step of the problem-solving workshop?

  • A. Identify the biggest root cause
  • B. Perform a root-case analysis
  • C. Agree on the problem to solve
  • D. Restate the new problem for the biggest root cause


Answer : C

How can teams use Iteration planning to stay aligned on their work?

  • A. By reviewing its processes before the next iteration
  • B. By sharing Stories that could be pairing opportunities
  • C. By agreeing on a meeting timebox
  • D. By committing to a set of goals to be delivered


Answer : D

What is a team’s primary goal in an Iteration?

  • A. Managing scope at the start of the Iteration
  • B. Sharing progress with the organization during the Iteration
  • C. Delivering working functionality at the end of the Iteration
  • D. Maintaining steady team syncs across the Iteration


Answer : C