Which product records any project outcomes perceived as negative by stakeholders?

  • A. Business Case
  • B. Project Plan
  • C. Communication Management Strategy
  • D. Project Product Description


Answer : A

What is the definition of a project outcome?

  • A. A measurable improvement that is perceived as an advantage by one or more stakeholders
  • B. The reason for the project
  • C. The result of the change derived from using the project's outputs
  • D. The project's specialist products.


Answer : C

Which is NOT a purpose of a Benefits Review Plan?

  • A. Define the period over which the cost-benefit analysis will be based
  • B. Describe how to measure the performance of the project's products in operational use
  • C. Define the scope, timing and ownership of the benefit reviews required
  • D. Describe how to measure and confirm any benefits that are to be realised after the project is closed


Answer : A

Which product documents the information needed to demonstrate continued business justification?

  • A. Business Case
  • B. Communication Management Strategy
  • C. Project Product Description
  • D. Quality Management Strategy


Answer : A

Which is NOT a purpose of a Benefits Review Plan?

  • A. Define the period over which the cost-benefit analysis will be based
  • B. Describe how to measure the performance of the project's products in operational use
  • C. Define the scope, timing and ownership of the benefit reviews required
  • D. Describe how to measure and confirm any benefits that are to be realised after the project is closed


Answer : A