Which describes the 'Implement' step within the recommended risk management procedure?

  • A. Project Support will allocate the risk budget to fund the selected risk responses
  • B. The risk owner will decide the best response to control the risk
  • C. The risk owner and the risk actionee will carry out activities to control and deal with the risk
  • D. The Project Manager will formulate the RiskManagement Strategy


Answer : C

Which is a purpose of the Risk theme?

  • A. Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
  • B. Establish a cost-effective procedure to identify, assess and control uncertainty
  • C. Establish mechanisms to control any unacceptable deviations from plan
  • D. Establish mechanisms to manage risks at the corporate or programme level of an organization


Answer : B

Why is a Project Brief produced?

  • A. To act as a trigger for the Starting up a Project process
  • B. To record the strategies andmanagement controls to be used by a project
  • C. To provide a full and firm foundation for the initiation of a project
  • D. To be used by the Project Board as a basis for reviewing the progress of a project


Answer : C

Which risk response type is appropriate to respond to an opportunity?

  • A. Accept
  • B. Fallback
  • C. Exploit
  • D. Transfer


Answer : C

Which is a purpose of a Product Description?

  • A. Provide the cost tolerance available for individual products
  • B. Define reporting frequency
  • C. Record the quality checks completed for the End Stage Report
  • D. Document the level of quality required of a product


Answer : D