A newly formed development team experienced difficulty with accurately estimating product backlog items. As a result, the team failed to deliver all of the features in the sprint backlog for the past two iterations.
What should the team do to improve the accuracy of their estimates?
Answer : B
Midway through a sprint, the scrum master identifies that reassigning a certain task could help the team meet its sprint's goals.
What should the scrum master do next?
Answer : C
During the iteration planning of a newly on boarded agile team, the product owner adds a set of high priority user stories into the iteration backlog.
What should the team do first to define the tasks need to implement the user stories?
Answer : A
A project's first iteration contains item A, and its second iteration contains item B. The first iteration is behind schedule, which will impact the second iteration.
Since items A and B are similar, a team member suggests beginning the design of item B.
What should the agile practitioner do?
Answer : C
An Agile team is under pressure to deliver an application. The product owner anticipates many change requests from customers once the product is released.
What should the agile team do?
Answer : B