A newly formed development team experienced difficulty with accurately estimating product backlog items. As a result, the team failed to deliver all of the features in the sprint backlog for the past two iterations.
What should the team do to improve the accuracy of their estimates?

  • A. Decrease the sprint time box until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint
  • B. Discuss estimating techniques in the daily scrum meeting
  • C. Increase the size of the development team until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint
  • D. Begin tracking estimated effort metrics as an input to performance evaluation


Answer : B

Midway through a sprint, the scrum master identifies that reassigning a certain task could help the team meet its sprint's goals.
What should the scrum master do next?

  • A. Alert the team that sprint goals might not be met and create an alternative plan
  • B. Obtain team buy-in to perform modifications to the sprint backlog
  • C. Have the sprint proceed as planned
  • D. Ask the team to decide if the task should be reassigned


Answer : C

During the iteration planning of a newly on boarded agile team, the product owner adds a set of high priority user stories into the iteration backlog.
What should the team do first to define the tasks need to implement the user stories?

  • A. Self-organize
  • B. Assign tasks to each team member
  • C. Meet with the customer
  • D. Identify the scrum master


Answer : A

A project's first iteration contains item A, and its second iteration contains item B. The first iteration is behind schedule, which will impact the second iteration.
Since items A and B are similar, a team member suggests beginning the design of item B.
What should the agile practitioner do?

  • A. Defer starting the design of item B until the second iteration is being planned
  • B. Proceed with the design of item B, since it will hasten the second iteration
  • C. Escalate the issue to the customer, and obtain their approval before starting the design of item B
  • D. Log the issue in the risk register, and request change control board (CCB) approval.


Answer : C

An Agile team is under pressure to deliver an application. The product owner anticipates many change requests from customers once the product is released.
What should the agile team do?

  • A. Demand frequent product reviews by the product owner
  • B. Continuously work with the product owner to do backlog refinement and product reviews
  • C. Have the product owner provide detailed requirement specifications to ensure the proper features are delivered
  • D. During the planning session, ensure the team is committed to deliver within the specifications


Answer : B