A contract cannot contain _____________.
Answer : A
Explanation:
A contract cannot contain illegal activities. A contract can contain other options available.
Which one of the following comes first in the project plan?
Answer : A
Explanation:
Scope statement comes first in the project plan. Scope statement is the written statement of project. It contains: Project objectives, Project justification, Project deliverables
You are project manager of a project. During the process of selecting the sellers, you reject one vendor because it doesn't have the manufacturing capability. This is an example of which selection tool?
Answer : B
Explanation:
A screening system rejects sellers that does not meet minimum requirements for the project.
______________ provides details about how the project scope may be changed.
Answer : D
Explanation:
The scope management plan provides details about how the project scope may be changed.
Which of the following technique to identify the underlying cause of a problem and take steps to prevent further occurrence?
Answer : A
Explanation:
Root cause analysis: A technique to identify the underlying cause of a problem and take steps to prevent further occurrence.