Which of the following process groups of the project life cycle integrates people and other resources to carry out the work defined in the project plan?

  • A. Executing
  • B. Planning
  • C. Closing
  • D. Initiating


Answer : A

When performing quantitative risk analysis, which of the following should be produced?

  • A. Control chart
  • B. Decision tree
  • C. Run chart
  • D. Scatter diagram


Answer : B

After identifying a change needed in the system, which of the following is the NEXT action the stakeholder should perform?

  • A. Inform the developer
  • B. Inform the resource manager
  • C. Inform the project manager
  • D. Inform the project sponsor


Answer : C

A project is experiencing quality issues with the deliverable product. Which of the following tools would be used to identify and prioritize the MOST commonly occurring issues?

  • A. Scatter diagram
  • B. Pareto chart
  • C. Ishikawa diagram
  • D. Trend analysis


Answer : B

When a project manager is leading the team through the norming stage of team growth, the project team:

  • A. is performing in a highly efficient manner.
  • B. has reached full capacity.
  • C. is seeing a decrease in productivity.
  • D. is working together and comfortable.


Answer : D