HP HPE0-S51 - Building HPE Data Center Solutions Exam

Page:    1 / 24   
Total 118 questions

You are working in a data center with multiple servers and need to update the iLO 5 user names and passwords on a regular basis.
Which tool enables you to streamline and automate this process?

  • A. iLO Amplifier Pack
  • B. Central Management Console
  • C. Agentless Management
  • D. RESTful API


Answer : A

You are troubleshooting a POST error on a HPE ProLiant rack-mount server. HPE support has directed you to test a minimum hardware configuration.
Which components should you remove? (Choose two.)

  • A. CMOS battery
  • B. all cooling fans
  • C. all expansion boards
  • D. all external storage media
  • E. redundant processors


Answer : DE

When should you use the HPE Switch Selector?

  • A. when you need to list the price information of the switches
  • B. when you need to select a switch VLAN configuration
  • C. when you need to compare features between multiple switches
  • D. when you need to perform a competitive analysis between vendors


Answer : C

A customer needs a solution that will maintain the data availability in their campus location. They require a multi-node system that can sustain failures, including a full building outage.
Which HPE storage platform meets the customer"™s needs?

  • A. StoreVirtual
  • B. StoreEasy
  • C. MSA
  • D. Nimble


Answer : C

DRAG DROP -
Match the HPE Tool with its use case. Select all that apply.
Select and Place:




Answer :

Page:    1 / 24   
Total 118 questions