A customer has a significant investment in open source software for performing in-memory analytics ? This workload is currently deployed an Linux and recent x86 hardware.
What advantage would POWERS provide to this customer?

  • A. Up to two times the cores per socket
  • B. Up to eight times the ChipKill correction rate
  • C. Up to four times the memory bandwidth
  • D. Up to six times the PCte bandwidth


Answer : D

Where should adapter configurations be validated before adding or rearranging adapter

  • A. HMC
  • B. SSIC
  • C. System Planning Tool
  • D. e-config


Answer : C

A customer has older genet aborts of Power servers that they went to manage with their
E870 from the same 7042-CR8 HMC running V8R8.2.0.
What is the earliest Power server generation that is supported with this HMC level?

A POWER4 -

B. POWER7 -

C. POWER6 -

D. POWER8 -



Answer : D

Which is a feature amiable with PowerVM that is not available with PowerKVM?

  • A. NFS storage support
  • B. Virtualization management through a CLI
  • C. Support for RHEL and SLES
  • D. HMC Attachment to Power Server


Answer : C

Which of the following can be moved from a 770 to an EB70 when doing a migration?

  • A. EXP30 SSD I/O drawer
  • B. Memory DIMMs
  • C. PCIe 5802/5877 I/O drawer
  • D. EXP24S SFFGen2-bay drawer


Answer : C