Which of the following elements can directly influence whether an availability check will be performed? (Choose two)
Answer : A,C
Based on which of the following dates is the availability check (ATP) carried out?
Answer : C
According to the system there is no stock available, but you still receive a confirmed schedule line in the sales order.
What is the reason for this confirmation?
Answer : A
If the material entered in the sales order is not available, how is the user alerted to this situation?
Answer : B
As a member of the project team, you are asked to set up the system so that user has to enter an order reason when processing a sales order. It should be possible to save the incomplete order, but further processing should not be possible until the Order Reason field is filled.
How do you implement this requirement?
Answer : B