SAP C_TSCM52_66 - SAP Certified Application Associate - Procurement with SAP ERP 6.0 EHP6 Exam

Page:    1 / 16   
Total 80 questions

You have received an order confirmation from a vendor.
What do you have to do before you can enter the confirmed delivery date and confirmed quantity in a purchase order item?

  • A. Set the Goods Receipt indicator.
  • B. Set the Confirmation Received indicator in the header.
  • C. Use a confirmation control key in the relevant purchase order item.
  • D. Set the Acknowledgement Required indicator in the vendor master of the relevant vendor.


Answer : C

Where do you define a fixed vendor for a specific period in time?

  • A. In the info record at client level (regular vendor)
  • B. In the quota arrangement at plant level
  • C. In the source list at plant level
  • D. In the material master at plant level


Answer : C

What are characteristics of material valuation at the moving average price?(Choose two)

  • A. If you book a subsequent debit for a quantity higher than the total quantity of valuated stock then a price difference posting is generated.
  • B. If the price in the purchase order is different from the moving average price then a price difference posting is generated at goods receipt.
  • C. The moving average price is equal to the total value divided by total quantity of valuated stock.
  • D. Goods movements are always valuated based on the moving average price from the material master record.


Answer : A,C

Which value of the creation indicator is shown in the tab Contact person when you create a purchase requisition manually?

  • A. Production Order
  • B. Direct procurement
  • C. Realtime
  • D. Material requirements planning


Answer : C

What does an account group control when you create vendor master records?(Choose three)

  • A. The partner determination procedure
  • B. The definition whether the vendor master record is a one-time account or not
  • C. The possible data retention levels
  • D. The reconciliation account in general ledger
  • E. The possible payment terms


Answer : A,B,C

Page:    1 / 16   
Total 80 questions