You want to use the function "Read PP master data" in the production order.
However, while calling the function you receive an error message.
What could be the reason?

  • A. The material availability check has been performed.
  • B. Goods movements have been posted.
  • C. The production order has been released.
  • D. Order papers have been printed.


Answer : B

Which objects can affect the calculation of capacity requirements for an operation?(Choose three)

  • A. Standard values (routing)
  • B. In-house production time (material master)
  • C. Transport time (routing)
  • D. Formulas (work center)
  • E. Operation control key (routing)


Answer : A,D,E

In the Customizing for requirements planning, a project team notices that the alternatives
P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type.
What does a firming type define?(Choose two)

  • A. Handling existing procurement proposals outside the planning time fence.
  • B. Handling existing procurement proposals within a planning time fence.
  • C. Handling new requirements within the planning time fence.
  • D. Handling new procurement proposals that need to be created due to new requirements within the planning time fence.


Answer : B,D

Which of the following scheduling types can only be used in capacity planning?

  • A. Midpoint
  • B. Forward
  • C. Only capacity requirements
  • D. Backward


Answer : A

Which types of objects can be changed with Engineering Change Management
(ECM)?(Choose three)

  • A. Task list
  • B. Work center
  • C. Production version
  • D. Bill of material
  • E. Material master


Answer : A,D,E