The technical completion of the current maintenance order was posted with a delay of 5 days.
What happens to the next planned date if you set the shift factor for early completion to 100%?
Answer : C
What can be determined using the offset within a maintenance strategy?
Answer : C
Which scheduling parameters are used in a multiple-counter plan? (Choose two.)
Answer : AB
How does a performance-based maintenance plan calculate the interval between start date and planned date?
Answer : D
The maintenance engineer creates a strategy plan with the call object maintenance order. Shift factors are set to 100%. Which date is relevant for the calculation of future planned dates if the maintenance work is delayed?
Answer : D