You work for an organization that uses Project Server 2013. Single-entry mode is disabled.
Team members enter updates in Project Web App (PWA) through the Tasks page. You need to select a tracking method that enables the following scenario:
-> During week one, a team member enters a total of 20 hours of actual work.
-> During week two, the team member modifies the total to 30 hours of actual work.
-> Following a save, the work value remains the same, and the remaining work value decreases.
-> Additionally, the percent of work complete increases.
Which tracking method should you use?
Answer : B
You are a project manager who has standard permissions, and your organization uses
Project Server 2013.
Some of your resources consistently update their assignments correctly. You want to accept their future updates without review.
You need to begin accepting their updates without review by using the least amount of effort possible.
What should you do?
Answer : A
You are a program manager who uses Project Server 2013 and Project Professional 2013.
You have administrative rights.
Your project managers create subprojects for your program-level master project. You insert the subprojects into your master project file by using Project Professional 2013. You are unable to save the master project file.
You need to ensure that your master project file appears with its subprojects when you use the Project Web App (PWA).
What should you do?
Answer : D
You are a project manager who uses Project Server 2013.
You want to use the Resource Center Availability function and the Assignment Work by
Resource view to see the proposed and active projects for a particular resource. However, you are only able to view part of the work load for the resource.
You need to view the complete work load for the resource.
Which two settings should you verify? (Each correct answer presents part of the solution.
Choose two.)
Answer : C,D
You are a project manager in an organization that uses Project Server 2013. You manage a project that has Baseline0 set. There are enterprise custom fields with formulas that make calculations by using the Baseline0 fields.
You are planning a major rescheduling in your project and intend to update the project baseline so the formulas in the enterprise custom fields take the new values of the baseline fields.
However, for future reference, you want to keep your original baseline.
You need to update the project baseline without losing the original values.
What should you do?
Answer : B