You are a project manager for a company that uses Project Professional 2013.
You are responsible for communicating the progress of your projects every month. Your company provides you with a Gantt Chart view that uses the standard Entry table.
You need to communicate the progress of tasks that have a finish date of either October 2 or October 22.
What should you do?
Answer : D
You are a project manager who uses Project Standard 2013.
Your current project has resources with the standard calendar as the base calendar. Some tasks of the project need to be done overnight so the night shift calendar is assigned to those tasks. When you assign a resource to one of these tasks, you get an error.
You need to correctly assign the resource.
What should you do?
Answer : D
You are a project manager for an organization that uses Project Professional 2013.
You are planning a project schedule that starts on March 1 and lasts four months.
However, the sponsor now asks that the project be delayed to have a finish date of
December 31.
Answer : B,D,E
You are a project manager who uses Project Professional 2013. You have worked on a project for four years and have created a very detailed project plan in Project Professional
2013. You use milestones as key deliverables, and you use summary tasks as phases.
Your company requests a presentation of the key deliverables for each phase of your project plan in a simple and consolidated view that fits in one Microsoft PowerPoint slide.
You need to ensure that phases and key deliverables are clearly shown in the timeline and are not confusing to the audience.
What should you do?
Answer : D
You are a project manager who uses Microsoft Project 2013.
A resource manager notifies you that your assigned resource is now only available 50% to work on the communication plan task. The estimated amount of work for the task remains the same at 16 hours. The task must also be completed within the original two-day commitment even though the resource is only available 50% of the time.
You need to bring on another resource to assist with the remaining 50% of the work while ensuring that the same amount of work gets done in the two days that were originally committed.
Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)
Answer :
Explanation:
Box 1: Assign the additional resource to the task.
Box 2: Set the task type to fixed work,
Box 3: Change both the new and existing resource units to 50%.
Note:
* For a fixed-work task
/ You can change the assignment units value and Project will recalculate the duration.
/ You can change the duration value and Project will recalculate peak units per time period.
The assignment units value is not affected.