When powering on a Vblock System what is the correct power up sequence?

  • A. Switches, AMP, SAN, UCS chassis, and UCS blades
  • B. Switches, SAN, UCS chassis, UCS blades, and AMP
  • C. Switches, AMP, UCS chassis, UCS blades, and SAN
  • D. Switches, SAN, AMP, UCS chassis, and UCS blades


Answer : A

What are three primary site survey considerations? (Choose three.)

  • A. Site information
  • B. Technical resources
  • C. Customer power requirements
  • D. Data center physical audit
  • E. Disaster recovery plan


Answer : A,C,D

Which EMC software is required to initialize a Vblock System 200 storage array?

  • A. Unisphere Service Manager
  • B. Unisphere Server Utility
  • C. VNX Installation Assistant
  • D. Unisphere Client


Answer : C

Which EMC software is required to upgrade code on a Vblock System 200 storage array?

  • A. Unisphere Service Manager
  • B. Unisphere Server Utility
  • C. VNX Installation Assistant
  • D. Unisphere Client


Answer : A

Which two statements are correct about Vblock System Release Certification Matrix (RCM) upgrades? (Choose two.)

  • A. The RCM must be applied by VCE certified resources.
  • B. When upgrading to a new RCM, all components may not require an upgrade.
  • C. The most recent RCM version must be applied.
  • D. An addendum to the RCM may be issued to address a bug or software issue.


Answer : B,D