Microsoft MB6-884 - Microsoft Dynamics AX 2012 Lean Manufacturing Exam

Page:    1 / 16   
Total 79 questions

You are posting a purchase receipt for a subcontracted service as part of a Lean production flow in Microsoft Dynamics AX 2012. To which ledger accounts does the transaction post?

  • A. Liability and Raw Material Inventory
  • B. Liability and Work In Process (WIP)
  • C. Raw Material Inventory and Work In Process (WIP)
  • D. Raw Material Inventory and Variance


Answer : B

Reference:http://dynamicscare.com/blog/index.php/activity-based-subcontracting/

Components have been consumed by a production flow.
When the backflush costing process is run at the end of a period, in what order are the consumed components processed?

  • A. transaction quantity order
  • B. receipt date order
  • C. FIFO order
  • D. LIFO order


Answer : C

Reference:
Microsoft Dynamics AX 2012, Lean Manufacturing: Production flows and activities, White
Paper, April 2011, p 38.

When does the Capable to Promise (CTP) functionality allow the user to see the availability of products in Microsoft Dynamics AX 2012? (Each correct answer presents a complete solution. Choose two.)

  • A. in a batch job after the sales order lines are entered.
  • B. When a scheduled Kanban is generated.
  • C. Automatically when an order is entered.
  • D. After the View pegging tree requirement is selected on the sales order.


Answer : B,D

Reference:
Microsoft Dynamics AX 2012, Lean Manufacturing:Kanban and Pull Based Manufacturing,
White Paper, July 2011, p 35.

Which cost is used to estimate the cost contribution of a subcontracted activity in Microsoft
Dynamics AX 2012 Lean manufacturing?

  • A. zero cost
  • B. the standard cost of the service product used to purchase the subcontracted service
  • C. the last cost of the service product used to purchase the subcontracted service
  • D. the amount from the purchase agreement line used to purchase the subcontracted service


Answer : B

Reference:
Microsoft Dynamics AX 2012, Lean Manufacturing: Production flows and activities, White
Paper, April 2011, p 45.

What is required to firm a planned order of type Kanban in Microsoft Dynamics AX 2012?

  • A. an event Kanban rule
  • B. a Kanban line rule
  • C. a fixed Kanban rule
  • D. a scheduled Kanban rule


Answer : D

Reference:
http://dynamicscare.com/blog/index.php/scheduling-kanbans-in-ax2012/

Page:    1 / 16   
Total 79 questions