On what is project baseline development established?

  • A. Approved product requirements
  • B. Estimated project cost and schedule
  • C. Actual project cost and schedule
  • D. Revised project cost and schedule


Answer : B

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

  • A. Work breakdown structure
  • B. Organizational breakdown structure
  • C. Resource breakdown structure
  • D. Bill of materials


Answer : A

What is the definition of project plan execution?

  • A. Integrating all planned activities.
  • B. Performing the activities included in the plan.
  • C. Developing and maintaining the plan.
  • D. Execution of deliverables.


Answer : B

What is a tool to improve team performance?

  • A. Staffing plan
  • B. External feedback
  • C. Performance reports
  • D. Co-Location


Answer : D

Which type of analysis is used to develop the communications management plan?

  • A. Product
  • B. Cost benefit
  • C. Stakeholder
  • D. Research


Answer : C